140 sites scanned and compartmentation drawings delivered in 12 weeks
A council needed accurate compartmentation drawings across its estate before installing new fire doors and carrying out fire-stopping works.
The challenge
The council was about to begin a programme of fire door replacement and fire-stopping works across 140 sites. Before contractors could start, it needed accurate compartmentation drawings for every building, and existing drawings could not be relied on.
What we did
We scanned every one of the 140 sites and produced a compartmentation drawing for each, showing compartment lines, fire-resisting construction and fire door locations.
Alongside the drawings, every building received a VR twin. These supported the council's dilapidation reports and gave it a lasting visual record of each site before works began.
The result
All 140 drawings and twins were delivered within the agreed 12-week timescale, giving the council and its contractors an accurate basis for the fire door and fire-stopping programme.